Orme House | June Construction Update

Orme House | June Construction Update

Construction on Orme House is well underway with the piling now completed to the new build block. Building Control inspections have been completed as the foundations have progressed, along with all other design work.

Pre-fabricated reinforcement cages have been delivered to site and fixing has commenced. The first concrete pour of the ground beams and pile caps will commence during w/c 18th June 2018. Associated drainage will also be completed in conjunction with the pile caps and ground beams.

Some minor alteration and adaptations have been completed to the existing building, although no significant new work is forecast until the delivery of the internal mezzanine steelwork, which has been ordered.

For more information on construction on Orme House email enquiries@pureinvestor.co.uk or call 0161 337 3890 to speak to a member of the consultancy team.

Get in touch, we're here to help.

For further details about Pure Investor or any of our property investment opportunities speak to our team.

SUBSCRIBE FOR OUR LATEST PROPERTY LAUNCHES AND UPDATES

Subscribe