Pure Investor are pleased to report, construction on Opto in Newcastle is progressing well and below is a summary of what has taken place so far.

  • The steel frame erection complete
  • Steel decking and stud welding is complete
  • Concrete floors pour complete
  • Internal drainage and substructure brickwork is complete
  • Internal cement boarding 95% complete
  • Windows 90% installed
  • Cladding 70% complete
  • M+E installation first fix complete
  • Cladding to outbuilding 95% complete
  • M+E second fix commenced

Overall, construction of Opto is on target for completion in September 2019.