Reliance House | January Construction Update

Reliance House | January Construction Update

Reliance House has undergone huge progress over the past few months, particularly on the fourth floor. Below is a broken-down detailed overview of what stage each floor of the conversion is at.

Fourth floor – construction progress

  • Apartment walls and ceilings and the first fix of electrical, plumbing and heating
  • 100% completed
  • Plaster finishes walls and ceilings – 95% completed
  • Skirting and architrave and the doors and ironmongery – 90% completed
  • Kitchen units and appliances, bathroom fittings, wall and floor tiling’s and decorations – 85% complete
  • Second fix electrical, plumbing and heating – 80% complete
  • General fixtures and fittings – 50% complete
  • Carpet floor finishes – 15% complete

Third floor – construction progress

  • Apartment walls and ceilings and the first fix electrical, plumbing and heating – 100% complete
  • Plaster finishes walls and ceilings, skirting and architrave – 95% complete
  • Bathroom fittings, doors and ironmongery – 90% complete
  • Kitchen units and appliances, wall and floor tiling and decorations – 85% complete
  • Second fix electrical, plumbing and heating – 80% complete
  • General fixtures and fittings – 40% complete

Second floor – construction progress

  • First fix electrical, plumbing and heating – 100% complete
  • Apartment walls and ceilings – 95% complete
  • Plaster finishes walls and ceilings, skirting and architrave – 90% complete
  • Wall and floor tiling and decorations – 85% complete
  • Doors and ironmongery, kitchen units and appliances – 80% complete
  • Bathroom fittings – 65% complete
  • Second fix electrical, plumbing and heating – 50% complete
  • General fixtures and fittings – 10% complete

First floor – construction progress

  • Apartment walls and ceilings and the first fix electrical, plumbing and heating – 100% complete
  • Plaster finishes walls and ceilings – 95% complete
  • Skirting and architrave – 85% complete
  • Doors and ironmongery – 80% complete
  • Decorations – 75% complete
  • Kitchen units and appliances – 70% complete
  • Second fix electrical, plumbing and heating – 55% complete
  • Bathroom fittings, wall and floor tiling – 50% complete
  • General fixtures and fittings – 30% complete

Ground floor – construction progress

  • Apartment walls and ceilings and the first fix electrical, plumbing and heating – 95% complete
  • Plaster finishes walls and ceilings – 90% complete
  • Skirting and architrave – 85% complete
  • Doors and ironmongery – 65% complete
  • Kitchen units and appliances and wall and floor tiling – 40% complete
  • Bathroom fittings – 30% complete
  • Decorations – 25% complete
  • Second fix electrical, plumbing and heating and general fixtures and fittings – 5% complete.

If you would like more information on Reliance House, don’t hesitate to get in touch on enquiries@pureinvestor.co.uk. Or call 0161 337 3890 to speak to a member of our consultancy team.