Reliance House has undergone huge progress over the past few months, particularly on the fourth floor. Below is a broken-down detailed overview of what stage each floor of the conversion is at.
Fourth floor – construction progress
- Apartment walls and ceilings and the first fix of electrical, plumbing and heating
- 100% completed
- Plaster finishes walls and ceilings – 95% completed
- Skirting and architrave and the doors and ironmongery – 90% completed
- Kitchen units and appliances, bathroom fittings, wall and floor tiling’s and decorations – 85% complete
- Second fix electrical, plumbing and heating – 80% complete
- General fixtures and fittings – 50% complete
- Carpet floor finishes – 15% complete
Third floor – construction progress
- Apartment walls and ceilings and the first fix electrical, plumbing and heating – 100% complete
- Plaster finishes walls and ceilings, skirting and architrave – 95% complete
- Bathroom fittings, doors and ironmongery – 90% complete
- Kitchen units and appliances, wall and floor tiling and decorations – 85% complete
- Second fix electrical, plumbing and heating – 80% complete
- General fixtures and fittings – 40% complete
Second floor – construction progress
- First fix electrical, plumbing and heating – 100% complete
- Apartment walls and ceilings – 95% complete
- Plaster finishes walls and ceilings, skirting and architrave – 90% complete
- Wall and floor tiling and decorations – 85% complete
- Doors and ironmongery, kitchen units and appliances – 80% complete
- Bathroom fittings – 65% complete
- Second fix electrical, plumbing and heating – 50% complete
- General fixtures and fittings – 10% complete
First floor – construction progress
- Apartment walls and ceilings and the first fix electrical, plumbing and heating – 100% complete
- Plaster finishes walls and ceilings – 95% complete
- Skirting and architrave – 85% complete
- Doors and ironmongery – 80% complete
- Decorations – 75% complete
- Kitchen units and appliances – 70% complete
- Second fix electrical, plumbing and heating – 55% complete
- Bathroom fittings, wall and floor tiling – 50% complete
- General fixtures and fittings – 30% complete
Ground floor – construction progress
- Apartment walls and ceilings and the first fix electrical, plumbing and heating – 95% complete
- Plaster finishes walls and ceilings – 90% complete
- Skirting and architrave – 85% complete
- Doors and ironmongery – 65% complete
- Kitchen units and appliances and wall and floor tiling – 40% complete
- Bathroom fittings – 30% complete
- Decorations – 25% complete
- Second fix electrical, plumbing and heating and general fixtures and fittings – 5% complete.