Pure Investor are pleased to share the progress over at Elizabeth Tower, Manchester.

PROGRESS TO JULY 2020

  • The 40th floor slab is complete with level 41 being prepared and will be poured soon Core of the tower is complete to level 43.
  • External Cladding to the tower installed up to level 26.
  • Watertight floor installed at level 16.
  • Laminate flooring ongoing at level 3 and installed on lower floors.
  • First fix dry lining walls have completed up to level 11 and first fix sprinkler works ongoing at level 8.
  • The electrical & plumbing & joinery first fix is currently at level 7.
  • Vents complete up to level 13.
  • Spray plaster up to level 4 and started on level 5
  • Tiling ongoing at level 3 soon to complete.
  • Kitchens ongoing at level 2; second fix joinery started on 22nd June
  • Low level brickwork complete to south and east elevations of low level podium structure: north elevation is around 80% complete.
  • Level 1 glazing and stone complete along with concierge rooflights & curtain walling.
  • Concierge internal trees installed in the lobby area.
  • Residents lounge spray plaster completed, with the flooring ongoing in this area.

Contact us today for further information.

Get in touch, we're here to help.

For further details about Pure Investor or any of our property investment opportunities speak to our team.

SUBSCRIBE FOR OUR LATEST PROPERTY LAUNCHES AND UPDATES

Subscribe